The latest two-week look ahead schedule for the West Avenue Neighborhood Improvements Project has been posted online. This schedule outlines ongoing and upcoming construction activities, including where crews will be working and what type of work to expect.
You can view the current schedule anytime under the “Two-Week Look Aheads” tab on the City’s project page: West Avenue Project Page
A summary of the contractor’s expected work is included below for your convenience. Thank you again for your continued support and patience as work progresses in the neighborhood. Here’s a quick recap of expected work through August 24, 2025:
Segment 2:
- Exploratory excavation continues within Segment 2 for existing utility verifications
- Watermain construction on Lincoln Court (Lincoln Road north to canal)
- Water Quality Well construction to start (Lincoln Road)
Segment 3:
- Exploratory excavation continues within Segment 3 for existing utility verifications
- Watermain construction on 16 Street
Safety Reminder
Your safety is our top priority. As work continues throughout the West Avenue Phase II Project, please don’t enter construction zones or move any signs, cones, or barricades. These safety measures are there to protect you and help keep the project moving smoothly. Staying informed will be key throughout the construction process, and our team remains committed to supporting the community every step of the way. Should you have any questions or need further information, please do not hesitate to reach out.
Contact
Should you have any questions regarding this project, please contact:
Heather M. Leslie, Public Information Liaison
Call/text 305.905.5876 or email: heather@hmlpublicoutreach.com
|