|
We've summarized the contractor's expected schedule through November 30, 2025. Please see it below, broken into the different areas of work. The contractor's full two-week look ahead schedule may be found online. It outlines ongoing and upcoming construction activities, including where crews are expected to be working and what type of work will be performed.
You can view the current schedule anytime under the “Two-Week Look Aheads” tab on the City’s project page: West Avenue Project Page
Thank you again for your continued support and patience as work progresses in the neighborhood.
Here’s a quick recap of expected upcoming work:
Pump Station (West Avenue next to the post office)
- FPL vault punch list Items
Segment 1 (West Avenue between the canal and just past the post office)
- Restoration and Harmonization of Segment 1 properties
Segment 2
(West Avenue between the post office and just south of Lincoln Road; Lincoln Road between Alton Road and the bay; and the Bay Road and Lincoln Court street ends):
- Locating underground utilities
- Sanitary sewer installation (Lincoln Road)
- Sanitary sewer installation (Bay Road)
- 20-inch water main installation (Bay Road)
- Water quality well construction (Lincoln Road east of West Avenue)
- Water quality well construction (Lincoln Road west of West Avenue)
- Water service connections to buildings (Lincoln Road and Bay Road)
Segment 3
(West Avenue from just south of Lincoln Road to 16 Street; and 16 Street between Alton Road and Bay Road):
- Locate underground utilities
New Water Main Testing
Testing of the newly installed water main is currently underway throughout the work zone. You may notice small taps of running water. Please do not touch, turn off or tamper with these taps. These tests are required by the Florida Department of Health and must run their full course without interruption. If they are stopped, the contractor (Ric-Man Construction Florida) would need to restart the process, which would cause delays. This testing is an important step to ensure the neighborhood’s water system is safe and ready for use and we appreciate your cooperation and patience while it is completed.
Safety Reminder
Your safety is our top priority. As work continues throughout the West Avenue Phase II Project, please don’t enter construction zones or move any signs, cones, or barricades. These safety measures are there to protect you and help keep the project moving smoothly. Staying informed will be key throughout the construction process, and our team remains committed to supporting the community every step of the way. Should you have any questions or need further information, please do not hesitate to reach out.
Contact
Heather M. Leslie, Public Information Liaison
Call/text 305.905.5876 or email: heather@hmlpublicoutreach.com
|