Exciting progress is happening! Concrete work in Phases 1A and 1B is now complete, and lighting has been installed. The project remains on schedule.
Meanwhile, curb installation continues in Phase 2B, and demolition in front of Webster Bank is expected to begin this Wednesday.
Nearly all major drainage work has been wrapped up, with only a few remaining areas in Phases 2A and 3A/3B still to be completed.
We appreciate the community’s ongoing patience as we work to bring long-term improvements to the heart of West Hartford Center.
|