Construction Alert

Week of February 26, 2024

Construction Highlights:


  • Wire installation on Overhead Wire System poles in the Pacific Electric Right-of-Way is ongoing.


  • Platform construction along Segment 3.


  • Platform construction along Segment 5.


  • Tree planting along Segment 4 is underway downtown. The work requires temporary street parking closures along the south side of 4th Street. “No parking” signs are posted 72 hours in advance of the start of the closures. Please follow posted “no parking” signs for current parking information.


Access will be maintained for all residents and businesses. Construction activities are dependent on weather and resource availability.


For information on how to process a construction-related, personal or property damage claim, please contact Tresa Oliveri at (714) 560-5374 or ocstreetcar@octa.net. She will provide information for the next steps in the process to file a claim with Walsh Construction.


Click here to check out featured businesses, services and events!


For specific work activities in your area, click on the map below.

Follow along a bird's-eye view of the OC Streetcar route!

Orange County’s first modern streetcar, OC Streetcar, recently completed an important project milestone. All of the paving along Santa Ana Boulevard has been completed allowing drivers, cyclists and pedestrians to travel from the Santa Ana Regional Transportation Center at Santiago Street all the way to Raitt Street where the track transitions to the Pacific Electric Right of Way without detours.


The OC Streetcar will increase connectivity for Santa Ana’s residents, businesses, restaurants and entertainment venues! Thank you to all our neighbors as we build this important transportation project.


Click below to view the video.

Parking in Downtown Santa Ana

Street parking in Downtown Santa Ana may be limited while construction is active. Several parking structures are available throughout the downtown area that offer free parking Monday through Friday, from 7 a.m. to 5 p.m. The first 2 hours of parking are free evenings and weekends:


  • 310 N Birch Street
  • 253 E 3rd Street
  • 420 N Main Street
  • 300 E 5th Street


The entrances to parking structures are accessible from 5th Street and 3rd Street.


Download a PDF of the parking map here.

Eat, Shop, Play




OCTA's Eat Shop Play program supports businesses located along the future OC streetcar route. Benefits to customers include special deals, invitations to community events and free parking for the first hour in nearby structures. Learn more at octa.net/eatshopplay.

About the Project

OC Streetcar is the first modern streetcar project to be built in Orange County and will serve Santa Ana’s historic and thriving downtown, which includes federal, state and local courthouses, government offices, colleges, an artists’ village and a thriving restaurant scene. It will operate along a 4.15-mile route that connects the Santa Ana Regional Transportation Center (SARTC) and a new transit hub at Harbor Boulevard and Westminster Avenue in Garden Grove.

Help OCTA design a walking and biking trail for your community!

Orange County Transportation Authority (OCTA), in cooperation with the cities of Garden Grove and Santa Ana, the California Department of Transportation (Caltrans), and the County of Orange, is advancing the OC Connect trail project. The project creates a 4-mile biking and walking trail connection between the downtown areas of Garden Grove and Santa Ana as well as to the Santa Ana River Trail and the countywide 66-mile bikeway - OC Loop. This project will improve the transportation network along the corridor and provide a safe, well-connected active transportation route. Sign-up to receive project updates!


Sign up now!

To share this e-blast, forward this link.